by Michelle Carter | Jul 26, 2026 | Expansion Update
ACT or Acoustical Ceiling Tile framing is being put in place. In this photo, you can see the framing for the ceiling tiles are installed in part of the youth shelving area. ACT tiles are “dropped” or suspended from the ceiling. This type of system is...
by Michelle Carter | Jul 24, 2026 | Expansion Update
Hi! Just over here building a...
by Michelle Carter | Jul 4, 2026 | Expansion Update
Did you know solar panels are part of the project? They are now installed on the library’s roof to help with the expanded library’s utility costs. ...
by Michelle Carter | Jun 28, 2026 | Expansion Update
Exterior brick placement begins! During initial planning, the design of the exterior was one point in the process needing state approval from a historical perspective by the State Historical Preservation Office, as the original Aram Library property is listed on the...
by Michelle Carter | Jun 22, 2026 | Expansion Update
Two weeks ago, the library team brought Mayor Ryan Schroeder, City Council adlerpersons and city staff, library board and Delavan-Delavan Lake board members together for a tour of the expansion project. Ever mindful of construction site protocols, expansion progress...
by Michelle Carter | Jun 13, 2026 | Expansion Update
Drywall installation is almost completed! If you’ve ever done your own drywall project, you may know that precision is overall to process filling in spaces like a Tretis™ game. Considered the bridge of a undertaking between framing and mechanicals towards...