by Michelle Carter | Aug 10, 2026 | Expansion Update
Viewing the maker space looking towards 5th Street, the cement floor is polished! While pretty, it also creates a strong, extremely durable surface for our maker space ready to tackle all upcoming projects glitter, glue – you name it! We fully expect this floor...
by Michelle Carter | Jul 27, 2026 | Expansion Update
Cabinetry is arriving and installation has begun! In the planning stages, many in the community shared their needs with the designers and building committee – more room for teens, study rooms, meeting room space, etc. The “feel” of the library was...
by Michelle Carter | Jul 26, 2026 | Expansion Update
ACT or Acoustical Ceiling Tile framing is being put in place. In this photo, you can see the framing for the ceiling tiles are installed in part of the youth shelving area. ACT tiles are “dropped” or suspended from the ceiling. This type of system is...
by Michelle Carter | Jul 24, 2026 | Expansion Update
Hi! Just over here building a...
by Michelle Carter | Jul 4, 2026 | Expansion Update
Did you know solar panels are part of the project? They are now installed on the library’s roof to help with the expanded library’s utility costs. ...
by Michelle Carter | Jun 28, 2026 | Expansion Update
Exterior brick placement begins! During initial planning, the design of the exterior was one point in the process needing state approval from a historical perspective by the State Historical Preservation Office, as the original Aram Library property is listed on the...